C1Yx Building Expansions
As part of General Motors’ investment in the Lansing Delta Township Assembly Plant, Aristeo constructed body shop additions of 66,000 SF and 113,000 SF, as well a general assembly addition of approximately 30,000 SF. The Lansing Delta Township plant sits on 320 acres and comprises nearly 3.7 million SF of manufacturing space.
Scope of work included a new cooling tower to accommodate utility capacity of building additions, complete installation of a new chiller, including all associated piping and controls, installation of a 1234yf refrigerant tank with associated trestle steel and utilities and over 209,000 SF. To optimize project construction, documentation, and contractor efficiency, Building Information Modeling (BIM) was used as a tool throughout the program.